Start date:  5 February 2018
Cost:  ¬£3 million approx
Status:  CURRENT
Type:  Improvement Scheme
End date:  January 2019
Programme:  

Progress report

A site compound is being constructed in January 2018 in preparation for construction, which will begin in February 2018. The first phase of work will include the construction of a cycle route on the A59 Northway, between Brooms Cross Road and Liverpool Road South.

What's next

In March, foundation works for the new gantry will start on the M57 - the gantry itself will not be installed until June 2018. From March to the end of the scheme, we will be constructing new high mast signals (including the foundations), installing 'intelligent cats eyes', and improving surfacing and road markings. Each of these phases will take place on a number of locations at Switch Island at the same time, so long as there is no clash in traffic management and diversion routes.

Other works include installation of signage and new lighting columns on the A59 Northway.

Timeline

Date Event
February 2018 Work begins
March 2018 New cycle route and new gantry construction work begins
January 2019 Expected completion of scheme

Why we need this scheme

This is a key route that accesses a number of amenities, as well as local employers such as the Port of Liverpool. Successive improvements to the roundabout mean it now has multiple arms. The most recent improvements have been the addition of a direct link from Switch Island to the A595 which bypasses the village of Thornton. The roundabout has a poor safety record with a high accident rate.

Aims

The primary aim is to improve safety for road users by encouraging them to reduce speeds and improve their lane discipline. This will be achieved by installing various signs, a new gantry and by improved road markings.

Improvements will include:

  • construction of a new motorway gantry
  • installation of high-mast traffic signals
  • improvements to cycle facilities
  • installation of ‚Äėintelligent cats eyes‚Äô - which light up in response to changing traffic lights
  • improvements to the road layout
  • carriageway surfacing

Project media files and documents

There are no images for this project
There are no videos for this project

Project timeline

Planned roadworks

Roadworks and Events for England

The latest incident information for England's motorway and trunk routes provided by Highways England

Location : The junction of the M58 and the A59 . Reason : Roadworks are planned. Status : Pending. Schedule : Expect disruption everyday between 20:00 and 06:00 from 23 April 2018 to 28 April 2018. Schedule : Expect disruption everyday between 20:00 and 06:00 from 30 April 2018 to 5 May 2018. Schedule : Expect disruption everyday between 20:00 and 06:00 from 7 May 2018 to 12 May 2018. Schedule : Expect disruption everyday between 20:00 and 06:00 from 14 May 2018 to 19 May 2018. Lanes Closed : All lanes will be closed.
Posted: April 21, 2018, 5:04 am
Location : The M58 eastbound between junctions J4 and M6 . Lane Closures : Lane three will be closed. Reason : Horticultural works are planned. Status : Pending. Schedule : From 21:00 on 27 April 2018 to 06:00 on 28 April 2018. Lanes Closed : There will be one of three lanes closed.
Posted: April 20, 2018, 8:10 pm
Location : The M53 southbound exit slip at junction J3 . Lane Closures : Lane one is closed. Reason : Roadworks. Status : Currently Active. Period : expect disruption until 05:30 on 23 April 2018. Lanes Closed : There is one of two lanes closed.
Posted: April 20, 2018, 8:05 pm
Location : The M58 eastbound between the M57 and junction J1 . Lane Closures : Lane one is closed. Reason : Roadworks. Status : Currently Active. Period : expect disruption until 06:00 on 23 April 2018. Lanes Closed : There is one of three lanes closed.
Posted: April 20, 2018, 7:04 pm
Location : The M58 eastbound entry slip at junction J1 . Lane Closures : Lane one will be closed. Reason : Litter clearance is planned. Status : Pending. Schedule : From 08:00 on 23 April 2018 to 15:00 on 23 April 2018. Lanes Closed : There will be one of two lanes closed.
Posted: April 20, 2018, 3:40 pm
Location : The M58 westbound exit slip at junction J4 . Lane Closures : Lane two will be closed. Reason : Roadworks are planned. Status : Pending. Schedule : From 09:00 on 23 April 2018 to 16:00 on 23 April 2018. Lanes Closed : There will be one of two lanes closed.
Posted: April 20, 2018, 3:02 pm
Location : The M53 southbound between junctions J3 and J4 . Lane Closures : Lane one is closed. Reason : Road repairs. Status : Currently Active. Period : expect disruption until 05:00 on 1 July 2018. Lanes Closed : There is one of three lanes closed.
Posted: April 20, 2018, 7:32 am
Location : The M53 northbound. Lane Closures : Lane one will be closed. Reason : Roadworks are planned. Status : Pending. Schedule : Expect disruption everyday between 09:30 and 15:30 from 24 April 2018 to 27 April 2018. Lanes Closed : There will be one of two lanes closed.
Posted: April 19, 2018, 10:40 am
Location : The M62 eastbound entry slip at junction J6 . Reason : Emergency barrier repairs are planned. Status : Pending. Schedule : From 21:00 on 23 April 2018 to 05:00 on 24 April 2018. Lanes Closed : All lanes will be closed.
Posted: April 18, 2018, 3:40 pm
Location : The M57 southbound exit slip at junction J3 . Lane Closures : Lane one will be closed. Reason : Horticultural works are planned. Status : Pending. Schedule : From 21:00 on 24 April 2018 to 06:00 on 25 April 2018. Lanes Closed : There will be one of two lanes closed.
Posted: April 17, 2018, 8:10 pm
Location : The M57 southbound between junctions J4 and J3 . Lane Closures : Lane one will be closed. Reason : Horticultural works are planned. Status : Pending. Schedule : From 21:00 on 24 April 2018 to 06:00 on 25 April 2018. Lanes Closed : There will be one of three lanes closed.
Posted: April 17, 2018, 8:10 pm
Location : The M57 northbound at junction J1 . Lane Closures : Lane two will be closed. Reason : Litter clearance is planned. Status : Pending. Schedule : From 21:00 on 23 April 2018 to 05:00 on 24 April 2018. Lanes Closed : There will be one of two lanes closed.
Posted: April 17, 2018, 10:01 am
Location : The M57 northbound between junctions J1 and J3 . Lane Closures : Lane two will be closed. Reason : Litter clearance is planned. Status : Pending. Schedule : From 21:00 on 23 April 2018 to 05:00 on 24 April 2018. Lanes Closed : There will be one of three lanes closed.
Posted: April 17, 2018, 10:01 am

Announcements

Breaking News: Traffic Information

Breaking News

The latest current breaking news items for England's motorway network

Regional Twitter feed

Keep up-to-date

Sign up for updates
Please leave feedback