M3 junctions 2-4a: smart motorwayRecently updated

We are currently making improvements to the M3 by constructing a smart motorway between junctions 2 and 4a. This section of the M3 is used over 130,000 vehicles a day and sees higher than normal levels of congestion at peak times.

Region:  South East
Start date:  18 February 2015
Cost:  £174 million
Status:  CURRENT
Type:  Major Scheme
End date:  June 2017
Programme:  Smart Motorways

Progress report

As part of the ongoing works to reconstruct Woodlands Lane Bridge at Windlesham; which sits across the M3 motorway around 2 miles east of junction 3, we successfully lifted the steel supporting beams into place during a full weekend closure.

For details of upcoming planned closures you can check our roadworks feed or view diversion routes.

You can also view diversion routes for overnight closures between junctions 3 and 4.

Using two cranes, 24 steel beams which will form the structural desk of the new bridge, were lifted and secured in place across the motorway.

During the weekend closure, we also planned to carry out 4000 tonnes of low noise resurfacing as part of the smart motorway works. We successfully carried out a substantial amount more than planned, with 5500 tonnes of low noise resurfacing being laid in total.

What's next

Woodlands Lane Bridge Works

  • columns will be installed in the verges for the new bridge, strengthening works will then be carried out
  • traffic management will be switched to enable us to work in the central reserve
  • works for the new bridge will then commence

Surfacing works

  • We will be resurfacing lanes 1 and 2 between junctions 2 and 3
  • We will be carrying out resurfacing works on the M3 slip road at junction 2 northbound to the M25 clockwise and on the M3 junction 4 northbound entry slip road

Drainage and concrete safety barrier works

  • the drainage and concrete safety barrier works in the central reserve between junctions 3 and 4a will continue

Other verge works

  • installation of communication infrastructure and cables
  • installation of safety fencing
  • re-installing sections of the environmental barrier (previously removed in order for works to be carried out)
  • construction of the foundations for signs that will be placed in the verges
  • install Variable Message Signs (VMS) and Advanced Motorway Indicator (AMI) signs onto the new gantries

View our gallery

Community news

The M3 project is a member of the Community Matters Partnership Project (CMPP). The CMPP is a collaboration of socially responsible, caring organisations who founded this project to make a lasting difference in the local community.

We want to give back to the community while we are here and since starting construction, we have undertaken various charitable and voluntary projects.

So far we have:

  • raised a total of £2450 over the last year from various fund raising events
  • donated to some of our nominated charities: Creating Futures charity - Save the Children - The Princes Trust and East Anglian Air Ambulance
  • continued to support Creating Futures, a local charity working with young disadvantaged children
  • rescued an injured swan and made contact with the Swan Support Organization which resulted in getting it’s injuries healed
  • gave a presentation to 150 senior school students at Hall Manor School on the running of a major civil engineering project
  • assisted at a Child Safety Event organised by the Rushmoor Voluntary Services
  • assisted with an Enterprise day at the Wavell School where pupils took part in a Dragons Den type exercise
  • assisted with mock interviews at Calthorpe Park School to help school children gain valuable interview skills preparing them for later life and their future careers
  • organised an outdoor classroom for Fernhill School in partnership with Fluor Construction and TAG Europe
  • held an art competition with local schools where twelve winning pictures, chosen by the M3 team were used in the 2016 M3 project calendar
  • presented to parents and students at a local school on the demolition of Woodlands Lane Bridge

In addition, the project has been awarded National Skills Academy status supported by Highways England and managed by the Construction Industry Training Board. The National Skills Academy for Construction is a project-based training concept.

We have provided several opportunities as part of the M3 project. So far we have:

  • supported 21 of our colleagues to achieve their NVQ qualification
  • provided 12 work experience placements for students aged 14-19, one of which was offered a trainee role within the Health, Safety & Environment team
  • supported one of our cleaning staff to gain a permanent role within the project team
  • appointed two young trainee lab technicians
  • setup a special needs placement programme

The Academy creates apprenticeships and work experience opportunities and encourages engagement with schools and colleges to promote careers in the construction industry. The project is continually audited by the Construction Industry Training Board and on our most recent audit we received a score of 94% out of a possible 100%!.

We take the concerns of residents very seriously and we have made sure we consider impacts upon the community in the project's ongoing development and design.

In order to build the scheme with as little negative impact as possible we are:

  • maintaining 3 lanes of traffic on both carriageways
  • have a 50mph speed limit in place for safety
  • providing a free recovery service for those in need through the works
  • limiting full closures to a minimum and managing when full closures take place to avoid conflicting with local events

In order to help keep traffic moving through the works, we employ a 24/7 CCTV system with full coverage throughout the scheme in order to pick up any incidents, accidents or vehicle breakdowns. All vehicles are recovered free of charge and as quickly as possible by our dedicated on-site vehicle recovery service. Drivers and their passengers are taken to our customer care centre where they can wait in a safe, comfortable environment, while making arrangements for their onward journey.

The project is also registered with the Considerate Constructors Scheme which was established to improve the image of construction. The project has audits throughout the year to assess what the project is continually doing to be a considerate constructor.

Environment impact

Our Environment Team works with a full-time ecologist on this project. We work together to protect wildlife located within the works area. Wildlife that has been found on site alongside the M3 junctions 2 to 4a smart motorway project and successfully relocated or removed is as follows:
  • slow worms (translocated to Chobham Common)
  • smooth newts (relocated to Hawley Meadows)
  • grass snakes (moved to safe/suitable location behind environmental barrier)
  • badgers - badger sett closed off using one way badger gates
We have gained approval from Surrey Wildlife Trust and Natural England to carry out small amounts of work within Chobham Common. We have carefully planned to make sure there are no negative impacts on the common due to construction works, without delaying our construction programme. The Site of Special Scientific Interest status of the common extends onto the motorway verge. Following works on these verges, Surrey Wildlife Trust will supply seeds from the common to add to the grass seed mix we will use for the verge. This will replenish the verge and maintain these important habitats. Our contractor Balfour Beatty has:
  • established between our contractor Balfour Beatty and the Senior Ranger of Surrey Wildlife Trust
  • carried out water monitoring on the common to demonstrate to Surrey Wildlife Trust that the water quality has not been reduced due to pollution from the motorway works
  • surveyed bird nesting sites before and during construction to show that the works were having no ill effects on protected nesting birds: woodlark, Dartford warbler and nightjar
We have produced some formal reports on environmental impact. You can find these under Publications.

The project team

  • Highways England
  • Balfour Beatty
Our contractor, tasked with delivering this project in accordance with our requirements
  • URS
  • Design engineer and our agent on-site

Project media files and documents

There are no images for this project
There are no videos for this project

Project timeline

Planned roadworks

Roadworks and Events for England

The latest incident information for England's motorway and trunk routes provided by Highways England

Location : The M3 eastbound entry slip at junction J3 . Reason : Road repairs. Status : Currently Active. Period : expect disruption until 07:00 on 25 June 2017. Lanes Closed : All lanes are closed.
Posted: June 24, 2017, 7:06 pm
Location : The M3 eastbound between junctions J3 and J2 . Reason : Roadworks. Status : Currently Active. Period : from 20:01 on 24 June 2017 to 07:00 on 25 June 2017. Lanes Closed : All lanes are closed.
Posted: June 24, 2017, 7:02 pm
Location : The M3 eastbound between junctions J3 and J2 . Reason : Road repairs. Status : Currently Active. Period : expect disruption until 07:00 on 25 June 2017. Lanes Closed : All lanes are closed.
Posted: June 24, 2017, 7:01 pm
Location : The M3 westbound entry slip at junction J3 . Lane Closures : Lanes 1 and 2 will be closed. Reason : Road repairs are planned. Status : Pending. Schedule : Expect disruption everyday between 20:00 and 05:30 from 26 June 2017 to 28 June 2017. Schedule : From 20:00 on 28 June 2017 to 06:00 on 29 June 2017. Schedule : From 20:00 on 29 June 2017 to 05:30 on 30 June 2017. Schedule : From 20:00 on 30 June 2017 to 07:00 on 1 July 2017. Lanes Closed : All lanes will be closed.
Posted: June 24, 2017, 6:01 am
Location : The M3 westbound between junctions J2 and J4A . Lane Closures : Lanes 1, 2 and 3 will be closed. Reason : Road repairs are planned. Status : Pending. Schedule : Expect disruption everyday between 20:00 and 05:30 from 26 June 2017 to 28 June 2017. Schedule : From 20:00 on 28 June 2017 to 06:00 on 29 June 2017. Schedule : From 20:00 on 29 June 2017 to 05:30 on 30 June 2017. Schedule : From 20:00 on 30 June 2017 to 07:00 on 1 July 2017. Lanes Closed : All lanes will be closed.
Posted: June 24, 2017, 6:01 am
Location : The M3 westbound entry slip at junction J4 . Lane Closures : Lanes 1 and 2 will be closed. Reason : Road repairs are planned. Status : Pending. Schedule : Expect disruption everyday between 20:00 and 05:30 from 26 June 2017 to 28 June 2017. Schedule : From 20:00 on 28 June 2017 to 06:00 on 29 June 2017. Schedule : From 20:00 on 29 June 2017 to 05:30 on 30 June 2017. Schedule : From 20:00 on 30 June 2017 to 07:00 on 1 July 2017. Lanes Closed : All lanes will be closed.
Posted: June 24, 2017, 6:01 am
Location : The M3 eastbound entry slip at junction J3 . Reason : Road repairs are planned. Status : Pending. Schedule : Expect disruption everyday between 20:00 and 05:30 from 26 June 2017 to 30 June 2017. Schedule : From 20:00 on 30 June 2017 to 07:00 on 1 July 2017. Lanes Closed : All lanes will be closed.
Posted: June 24, 2017, 6:01 am
Location : The M3 eastbound entry slip at junction J4 . Lane Closures : Lanes 1 and 2 will be closed. Reason : Road repairs are planned. Status : Pending. Schedule : Expect disruption everyday between 20:00 and 05:30 from 26 June 2017 to 30 June 2017. Schedule : From 20:00 on 30 June 2017 to 07:00 on 1 July 2017. Lanes Closed : All lanes will be closed.
Posted: June 24, 2017, 6:01 am
Location : The M3 westbound between junctions J2 and J3 . Lane Closures : The hard shoulder and lane 3 are closed. Reason : Road repairs. Status : Currently Active. Period : expect disruption until 05:30 on 1 July 2017. Lanes Closed : There is one of three lanes closed.
Posted: June 20, 2017, 11:20 pm
Location : The M3 westbound between junctions J2 and J5 . Reason : Roadworks. Status : Currently Active. Period : from 02:35 on 7 April 2017 to 06:00 on 1 July 2017.
Posted: June 20, 2017, 11:20 pm
Location : The M3 eastbound between junctions J3 and J2 . Lane Closures : The hard shoulder and lane 3 are closed. Reason : Road repairs. Status : Currently Active. Period : expect disruption until 05:30 on 1 July 2017. Lanes Closed : There is one of three lanes closed.
Posted: June 20, 2017, 11:20 pm

Announcements

Breaking News: Traffic Information

Breaking News

The latest current breaking news items for England's motorway network

Regional Twitter feed

Keep up-to-date

Sign up for updates
Please leave feedback