A21 Tonbridge to Pembury duallingRecently updated

Upgrade of the A21 to a 2 lane carriageway between Tonbridge and Pembury.

Region:  South East
Start date:  April 2015
Cost:  £69.7 million
Status:  CURRENT
Type:  Major Scheme
End date:  Summer 2017
Programme:  

Progress report

The Fairthorne Bridge was completed and traffic was switched over it on the 10th June. This allowed the last section of the old A21 to be removed and for the construction of the northbound embankment to the Fairthorne structure to commence, and the earthworks to construct the Fairthorne West access roads.

Scheme delay

Unfortunately we have had to delay completion of this scheme due to contamination found on the site. This contamination includes Friable asbestos which if not handled correctly, could be released into the surrounding environment and be harmful. Since the discovery the team has removed over 35,000 tonnes of contaminated soils.

The additional measures we have put in place to treat and remove the contamination from the site mean we are now looking at completing the work in Summer 2017 and not December 2016 as previously advertised.

What next?

We will continue with:

  • construction of the Blackhurst lane footbridge
  • completion of the Northbound Carriageway between Longfield bridge and Fairthorne bridge
  • work on the non-motorised user route across the project

Timeline

Date Event
December 2009 Orders published
October 2010 Spending review
May 2012 Funding announced
May 2013 Public inquiry
May 2014 Secretary of State announcement
April 2015 Start of works
Summer 2017 End of works

Why we need this scheme

Between the M25 and Tonbridge the A21 is a 2 lane carriageway standard with grade separated junctions, limited access and no central reserve gaps. Between Tonbridge and Pembury the standard drops to single carriageway with poor horizontal and vertical alignment and many individual accesses to properties, farm fields and woodlands. Approximately half way along the scheme there is a petrol station on the east side and junctions with two minor roads, Dislingbury Road and Pembury Walks, either side of the petrol station. This causes traffic congestion and delays on the A21, particularly due to right turning traffic. There are no footways and verges are either very narrow or non-existent. This single carriageway section of the A21 experiences severe congestion throughout the day and particularly at peak times and has a poor accident record with an average accident rate (expressed as accidents per million vehicle kilometres) about 20% higher than the default value for a road of this type.

The scheme in details

The new dual carriageway will broadly follow the line of the existing A21 with a new junctions at Fairthorne (by the petrol station) and at Longfield Road, replacing the existing roundabout at the southern end of the scheme. At the northern end, there will be a minor change to the line of the slip road from the Vauxhall Lane roundabout where it joins the A21. Parts of the existing A21 will be retained to provide access to houses, businesses, fields and woodland. A new bridleway for pedestrians, cyclists and horse riders will be provided along the whole length of the scheme. A new footbridge will be provided across the Pembury Bypass at Blackhurst Lane, replacing the existing crossing.

Aims

The main objectives of the scheme are to:
  • relieve congestion
  • improve safety for all road users
  • improve journey time reliability
The environmental objectives of the scheme are to:
  • mitigate the impact of the scheme on the AONB
  • minimise the adverse impact on the RSPB reserve and the Scheduled Ancient Monument
  • minimise the impact on ancient woodland

Environmental impact

We have surveyed the local area to assess the effect the scheme will have on the landscape and on plant and animal life. The results of the surveys and the measures we propose for reducing the effect of the scheme are contained in the envrionmental statement and are summarised in the non technical summary of the environmental statement. The link to these documents can be found on the ‘publications’ tab. During construction we will use best practice to safeguard the local environment and will plan the construction works to minimise adverse effects on the local community and the environment.

Ancient woodland

The scheme entails the unavoidable loss of 9Ha of ancient woodland for which 18Ha of translocated and planted woodland will be provided in mitigation. These areas will be managed for 25 years. In addition, 27Ha of existing woodland will be managed for 10 years while the new planting becomes established.

Local communities and land use

Parts of the existing A21 will be retained to provide access to houses, businesses, fields and woodland. Earthmounds and planting will be used to screen the A21 from properties, with noise fences included where they will be effective. The scheme will require additional land, most of which is good quality arable farmland or woodland. Four houses and 1 barn will need to be demolished to build the scheme. A new route for pedestrians, cyclists and horse riders will be provided along the length of the scheme, and an additional pedestrian and cycle bridge provided at Blackhurst Lane to facilitate access to Pembury Hospital.

Noise and vibration

Noise fences and earth mounds with planting will be provided to ensure that all residences currently close to the line of the existing A21 experience a reduction in noise level. Other areas further away from the A21 may experience a negligible increase in noise levels.

Air quality

The majority of affected residential properties may experience improved local air quality as a result of the scheme proposals and because of the reduced traffic congestion. Air pollutant concentrations at properties near to the road will not exceed the levels that are set to protect human health.

Landscape

Substantial areas of trees, shrubs and grassland will be planted, with the intention of fitting into the existing pattern of hedgerows, woodlands and pasture fields. Native species that are local to the area will be used where possible. The new junctions and road bridges will initially be intrusive features of the scheme but over time the extensive planting will create effective screening.

Wildlife and nature conservation

The Tonbridge to Pembury section of the A21 comprises a variety of habitats including woodland, hedgerows, grassland, streams and ponds. Protected species found during our surveys include bats, dormice, badgers, breeding birds, great crested newts and reptiles. Although areas of woodland will be lost to the scheme, a wide variety of mitigation measures have been included to limit or compensate these impacts. The project team has consulted with statutory bodies to ensure that with mitigation the long-term effects on most species will be neutral, and the character of the landscape preserved.

Water

The existing water environment will be protected by using drainage balancing and treatment ponds and facilities to contain pollutants. These measures will improve the quality of the water draining from the road system and ensure that there will be no increased risk of flooding in the area.

Historic environment

The scheme runs through the High Weald an area inhabited by man for at least 6000 years. There is evidence of Iron Age, Roman and Medieval activity in the wider landscape. The High Weald landscape is formed of small fields and woodlands dating from Medieval and Saxon periods and the scheme has been designed to retain this historic form of the landscape. So that the scheme has no effect on the Castle Hill Iron Age hillfort it will be necessary to demolish a Grade II listed farmhouse and barn. As a condition of the planning consent we will photograph and record the buildings before demolition and the barn will be carefully taken down and re-erected at a historic buildings museum. The farmhouse itself is not unique and has been altered a lot during its lifetime, so does not warrant re-erection.

Archaeology

Castle Hill brickworks preservation by record, where we photographed, sketched and recorded in detail our findings was completed.

Project media files and documents

There are no images for this project
There are no videos for this project

Project timeline

Planned roadworks

Roadworks and Events for England

The latest incident information for England's motorway and trunk routes provided by Highways England

Location : The A21 northbound between the A225 and the junction with the M25 . Lane Closures : Lane two is closed. Reason : Horticultural works. Status : Currently Active. Period : expect disruption until 06:00 on 21 July 2017. Lanes Closed : There is one of two lanes closed.
Posted: July 20, 2017, 8:03 pm
Location : The A21 northbound. Reason : Roadworks. Status : Currently Active. Period : from 20:03 on 20 July 2017 to 06:00 on 21 July 2017. Lanes Closed : All lanes are closed.
Posted: July 20, 2017, 7:05 pm
Location : The A21 northbound between the A262 and the junction with the A228 . Lane Closures : Lane one is closed. Reason : Road repairs. Status : Currently Active. Period : expect disruption until 06:00 on 21 July 2017. Lanes Closed : There is one of two lanes closed.
Posted: July 20, 2017, 7:02 pm
Location : The A21 northbound between the A228 and the junction with the A225 . Reason : Road repairs. Status : Currently Active. Period : expect disruption until 06:00 on 21 July 2017. Lanes Closed : All lanes are closed.
Posted: July 20, 2017, 7:02 pm
Location : The M26 westbound between junction J2A and the M25 . Lane Closures : Lane one will be closed. Reason : Road repairs are planned. Status : Pending. Schedule : From 22:00 on 20 July 2017 to 05:30 on 21 July 2017. Lanes Closed : There will be one of two lanes closed.
Posted: July 20, 2017, 4:21 pm
Location : The A21 northbound between the A228 and the junction with the A26 . Reason : Roadworks. Status : Currently Active. Period : from 01:39 on 18 May 2017 to 06:00 on 20 September 2017.
Posted: July 20, 2017, 4:21 pm
Location : The A21 northbound entry slip from the A26 . Reason : Horticultural works are planned. Status : Pending. Schedule : From 20:00 on 26 July 2017 to 06:00 on 27 July 2017. Lanes Closed : All lanes will be closed.
Posted: July 20, 2017, 4:21 pm
Location : The A21 northbound between the A225 and the junction with the M25 . Lane Closures : Lane two will be closed. Reason : Horticultural works are planned. Status : Pending. Schedule : Expect disruption everyday between 21:00 and 06:00 from 24 July 2017 to 26 July 2017. Lanes Closed : There will be one of two lanes closed.
Posted: July 20, 2017, 4:21 pm
Location : The M26 eastbound between the M25 and junction J2A . Reason : Roadworks are planned. Status : Pending. Schedule : Expect disruption everyday between 09:30 and 16:00 from 21 July 2017 to 26 July 2017.
Posted: July 20, 2017, 4:21 pm
Location : The A21 southbound between the A26 and the junction with the A228 . Reason : Roadworks. Status : Currently Active. Period : from 01:42 on 18 May 2017 to 06:00 on 20 September 2017.
Posted: July 20, 2017, 4:21 pm
Location : The M26 westbound between junction J2A and the M25 . Lane Closures : Lane one will be closed. Reason : Litter clearance is planned. Status : Pending. Schedule : From 22:00 on 25 July 2017 to 05:00 on 26 July 2017. Lanes Closed : There will be one of two lanes closed.
Posted: July 20, 2017, 4:21 pm

Announcements

Breaking News: Traffic Information

Breaking News

The latest current breaking news items for England's motorway network

Regional Twitter feed

Keep up-to-date

Sign up for updates
Please leave feedback